| Client: |
Red Band Inc., Fred.Olsen Production A.S. for Maersk Oil |
| Project: |
World’s largest tanker T/T Jahre Viking to FSO
Knock Nevis |
| Project Status: |
Project completed in 2004 |
| Project Scope: |
|
- Fabricating and installing heli-deck, 11P pump room, HPU room, import a
nd export manifold, metering skid platform, IG mast, Cantilever hose handling platform, deck crane foundations, Fwd pump room and Fwd generator room.
- The following were fitted: deck cranes, hawser handling winch, chain stopper and HPU. Pipe work involves, new Import and export line, decanted water circulation and offloading line, metering skid hook-ups, double valve separation, raising of bell-mouths in all the tanks, new stripping line, extension of fire & foam line, complete renewal of hydraulic lines.
- Electrical work like up-grading fire and gas system, PA/GA system, navigational system, tank temperature and pressure monitoring system.
- Fire equipment such as Sprinkler system and Novec system and CO2 system in 11P Pump room.
- Steel refurbishment in tank interior, engine room, pump room, accommodation and tank internal coating work.
- Steel renewal of approximately 1000 tonnes.
- ER Boiler and Turbine refurbishment.
- Main & auxiliary machinery refurbishment.
- Refurbishment of part of the accommodation, HVAC system and cargo pumps.
- Routine dry-docking.
|
|
Back |
|
| Client: |
Mercator Lines |
| Project: |
Tanker to FSO Prem Pride |
| Project Duration: |
2009-2010 |
| Project Scope: |
|
-
Fabricating and installing new heli-deck and outfitting.
- Fabricating and installing bow loading A-frames and piping to existing drop line.
- Additional accommodation for 25 people by adding additional bunks.
- Installing new fresh water generator and related pipe modification.
- Installing CCTV cameras and chain stopper load cells.
- Dry docking and repair.
|
|
Back |
|
| Client: |
Teekay Shipping (Norway) As for Occidental Petroleum Corporation |
| Project: |
Shuttle tanker to FSO Falcon Spirit |
| Project Duration: |
July 2009 – November 2009 |
| Project Scope: |
|
- Blasting and coating of ballast tank, cargo tanks, deck and external hull.

- Steel repair in tanks, installation of fatigue brackets and other miscellaneous items.
- Docking and general maintenance.
- Upgrading and modifying cargo system, Inert Gas & vent system and firefighting system.
- Upgrading electrical system and installing SDS and ESD systems.
- Overhauling of propulsion system and ER machinery.
- Upgrading HVAC system.
- Modifying living quarters.
- Relocating heli-deck.
- Installing new Fire & Gas alarm system and Public Address & Communication system.
|
|
Back |
|
| Client: |
EuroNav and Overseas Shipholding Group for Maersk Oil |
| Project: |
ULCC TI Asia to FSO Asia |
| Project Duration: |
October 2008 – November 2009 |
| Project Scope: |
|
- Grit blasting and painting of cargo tanks covering an area of 275,000m2.
- Installing approximately 6,000 metres of additional cargo pipelines in tanks and on deck; 1,200 new valves in the cargo pipes; five new generators and two new boilers in engine room;
metering skid, cranes and import and export manifold; 24,000 metres of new heating-coil in cargo tanks.
- Fabricating and setting up a structure for accommodation.
- Fabricating and installing new pipe rack structure on deck using 700
tonnes of steel.
- Assembling and installing new Aluminum heli-deck.
- Structure modification and installing two offloading hose reels.
- Renewing existing hydraulic line as well as installing approximately
50,000 metres of new line.
- Adding new electrical cable trays and power as well as control cabling.
|
|
Back |
|
| Client: |
EuroNav and Overseas Shipholding Group for Maersk Oil |
| Project: |
ULCC TI Africa to FSO Africa |
| Project Duration: |
January 2009 – March 2010 |
| Project Scope: |
|
- Grit blasting and painting of cargo tanks covering an area of 275,000m2.

- Installing approximately 6,000 metres of additional cargo pipelines in tanks and on deck; 1,200 new valves in the cargo pipes; five new generators and two new boilers in engine room; metering skid, cranes and import and export manifold; 24,000 metres
of new heating-coil in cargo tanks
- Fabricating and setting up another structure for accommodation.
- Fabricating and installing new pipe rack structure on deck that uses 700 tonnes of steel.
- Assembling and installing new Aluminum helideck.
- Structural modification and installing two offloading hose reels.
- Renewing existing hydraulic line as well as installing approximately 50,000 metres of new line.
- Adding new electrical cable trays and power as well as control cabling.
|
|
Back |
|
| Client: |
BW Offshore for Murmansk Commercial Seaport |
| Project: |
Tanker to FSO Berge Pioneer |
|
Project Status: |
Project completed in 2003. |
|
Project Scope: |
|
- Tank coating.

- Installing heating coils in all cargo tanks.
- Modifying loading and discharging manifolds.
- Installing mooring systems.
- The installation of heating coils were necessary due to the ship’s operating location is in Murmansk Russia, where the winter temperature dips below – 30 deg C.
|
|
|